Object naming standard
Rules for tag naming and numbering: a single identifier for the functional location and the equipment item that survives from design to decommissioning
Asset data management is more than a software platform. It requires clearly defined rules for what data is delivered, when it is delivered, how it is validated, who is responsible, and how non-conformities are resolved
A Unified Engineering Data Warehouse cannot be deployed on a project where the corresponding business process does not exist or does not work. The minimum condition is a set of standards for object naming, 3D modelling, and document numbering and classification
Our team has the experience and competencies to develop and implement the methodologies KRIDIUM needs to work on your project
Rules for tag naming and numbering: a single identifier for the functional location and the equipment item that survives from design to decommissioning
Requirements for developing and controlling the 3D model: scope, accuracy, element naming rules and the link between geometry, tags and documents
One system of document identifiers and types, letting every document be linked to a specific object, system and life-cycle stage
The cycle repeats throughout the project: data is accepted regularly, checked against formal criteria and returned to the contractor with findings until it is fit for operations
Functional locations, equipment items, classes and characteristics. Checked against the project data management and reference data guidelines
Documents, P&ID, passports and datasheets. Checked against the document numbering and classification standard or the project specifications
3D models of the units. Checked against the 3D model development and control standard, including the link between geometry and tags
The process works only when data responsibilities are formally defined in contracts - not left to informal agreements
| Role | Key Responsibilities | Frequency |
|---|---|---|
| The owner’s data management team | Requirements and standards, data acceptance and validation, formal findings, contractor training, user access to validated data | Continuous, clarification sessions once or twice a week |
| EP / EPC contractor | Delivering data in the owner’s templates, internal quality control, passing requirements down to subcontractors and manufacturers, correcting findings at its own expense | At least every two months, monthly during the active phase |
| Equipment vendors and manufacturers | Data and documentation for packaged deliveries, broken down to individual equipment items and the characteristics needed for passports | According to the delivery and acceptance schedule |
| Project management | Including data requirements in contracts from day one and tying data delivery to payment milestones | At the contract preparation stage |
| The owner’s project office | Monitoring compliance with tagging rules in documentation | Continuously during project execution |
If an engineering data management process is not yet in place, we establish it around the specific requirements of your project - from an initial maturity assessment to a fully operational data acceptance workflow
We assess which standards and processes already exist, where data is lost and what contractual requirements are in force
Tag naming and numbering, the classifier and reference data, 3D model requirements, document numbering and classification
Appendices to EP / EPC contracts and technical conditions: data scope, templates, delivery deadlines, links to payment milestones
Configuring KRIDIUM for the project information standard, training contractors, the first acceptance and findings cycles